Scope of Work: Provide labor and materials to improve the section of Millbend Loop Pathway located on the east side of Fernridge. One additional section is located between N. Timber Top and Doe Run. The Project includes the removal and replacement of an estimated 8,304 s.f. of pathway asphalt and the construction of a 2” asphalt overlay to approximately 41,880 s.f. identified sections of the Millbend Loop. The project also includes, but is not limited to, construction of eight (8) ADA compliance ramps and stencils.
|